Segment 3B

Length:
10.2 miles

Responsible Entity:
NET RMA

Project Type:
TOLL ROAD

From:
SH 31

To:
I-20

Initial Section:
2-Lane Undivided

Ultimate Section:
4-Lane Divided

Status:
Completed 

Opened: March 28, 2013

Toll 49 Segment 3B was delivered using the Design-Build development concept. This segment extends from SH 31 north to I-20, a distance of approximately 10.2 miles.  CH2M Hill, the Design-Build developer, was selected in June 2010.

The NET RMA received funding for Toll 49 Segment 3B through a State Infrastructure Bank Loan and a Toll Equity Loan provided by TxDOT.

Construction took approximately 22 months, with Toll 49 – Segment 3B opening to traffic as a Toll Road on March 28, 2013.